Electron test beam meeting ^^^^^^^^^^^^^^^^^^^^^^^^^^ August 23, 2004 ECAL status: ECAL QM model and mechanical structure needs at EIB+BDR ready and tested with LAPP daq chain Pisa DAQ will be setup during this week with the help of LAPP folks Needed 2 weeks for testing. Installation foreseen for the end of week 37 (Friday Sep 10) TRK status: DAQ almost finished. Installation of the whole chain during this week at UniGe. Needed 1 day for cabling (Sep 3) and 1 day for installation (Sep 6). Installation: Cables from barrack to zone should be installed BEFORE sensitive material (detectors). Both TRK and ECAL need 1 working day for this activity. It has been decided to do it FRIDAY Sep 3. By that time all supports should be installed and positioned in the zone. This means that concrete blocks for TRK telescope and drive table for ECAL as well as racks needed should be there. Tracker alignment: Juan's alignment routine. First ladder inside magnet fixed as reference plane. Schedule: For a detailed schedule see Martin's proposal